Opinion:
COP31 didn’t land a big deal. EV charging will carry on anyway.

COP31 closed in Antalya on Sunday without a deal. The EU and others rejected the final draft, which left out any mention of fossil fuels, and disagreements over climate finance didn’t help. A new agreement now looks unlikely before next year.

For those of us working in EV charging in England and Wales, my view is that this changes less than you’d think.

Nobody ever installed a charger because of a summit declaration. They get built because of domestic policy, commercial appetite and a lot of contracts. The ZEV mandate is pushing the market towards electric, and the Public Charge Point Regulations are raising the bar on reliability, contactless payment and pricing transparency. A global deal would have been a helpful tailwind, but the sector isn’t waiting for one.

Even the draft that failed pointed the same way. It called for expanding and modernising electricity grids, and for electricity to make up 35% of global final energy consumption by 2035. It wasn’t adopted, but it’s a fair sign of where things are heading.

Strip away the headlines and most charging deals hinge on the same few things:

  • Land: who has the right to install and run a charger, and what happens if the site is sold or mortgaged.
  • Planning: whether the scheme fits within permitted development or needs a full application. England’s permitted development changes are making it quicker and cheaper to install larger, higher-powered public charging hubs, so the answer on any site depends on which rules apply when you apply.
  • Grid: a perfect site with no timely connection is just a car park, and no summit text will fix that.
  • Substations: the DNO often needs its own lease, and in some cases it may require a transfer of the freehold. Substation leases can be slow to agree, and the DNO’s legal fees often fall on the landlord or operator.
  • Term and rent: lease terms of 10 to 15 years are typical, with either a fixed or turnover rent. Revenue shares also bring significant reporting obligations that people tend to underestimate.

With no headline deal, I’d expect the focus to stay with national policy: grid access, reliable public charging, and the next wave of sites, such as workplaces, retail, residential blocks and fleet depots. That mix of policy, property and power is where the interesting work is. It also means the landowners, operators and lawyers around the table have more say over the pace of rollout than any negotiator in Antalya.

I’d be keen to hear how others are seeing it. Are COP outcomes shaping your conversations, or is it all about the grid?

SHARE

This update is for general purposes and guidance only and does not constitute legal or professional advice. You should seek legal advice before relying on its content. Greenwoods Legal Services Limited is a limited company, registered in England, registered number 16115882. Our registered office is Queens House, 55-56 Lincoln’s Inn Fields, London, WC2A 3LJ. Authorised and regulated by the Solicitors Regulation Authority, SRA number 8011813. Details of the Solicitors’ Codes of Conduct can be found at www.sra.org.uk. All instructions accepted by Greenwoods Legal Services Limited are subject to our current Terms of Business. VAT Reg No: 502 6933 06. We do not tolerate harassment or abuse of our people by anyone, including clients, visitors and suppliers. If it happens, we will act.




    By completing and submitting this form, you consent to Greenwoods Legal Services Limited processing your personal data to contact you in relation to your enquiry and to provide you with any other materials and information about our services that Greenwoods Legal Services Limited reasonably believes will be of interest to you. You are free to withdraw your consent at any time by emailing [email protected]